Material availability check is one of the key integrations provided by SAP to check if the required material available or not during different order processing. Material Availability check in the maintenance order is one of the useful functionalities that integrates PM and MM module. When we plan materials in the maintenance order, we can either check the availability before the order is released or the system can do it automatically when the order is released.
Pre-requisites
- Plant Maintenance Configuration
- Material Master data Maintenance
Plant Maintenance Configuration
1. Define Checking Rules
Plant
Maintenance and Customer Service – Maintenance and Service Processing –
Maintenance and Service Orders – Functions and Settings for Order Types –
Availability Check for Material, PRTs, and Capacities – Define Checking Rules
2. Define Scope of Check
Plant
Maintenance and Customer Service – Maintenance and Service Processing –
Maintenance and Service Orders – Functions and Settings for Order Types –
Availability Check for Material, PRTs, and Capacities – Define Scope of Check
For Individual Requirements
This document will deal only with
Availability Check 02 (Individual Requirement)
3. Define Inspection Control
Plant
Maintenance and Customer Service – Maintenance and Service Processing –
Maintenance and Service Orders – Functions and Settings for Order Types –
Availability Check for Material, PRTs, and Capacities – Define Inspection
Control
This configuration needs to be done
with a combination of Plant / Order type / Availability Check
* Check material availability when
saving order
* Assign the Checking rule created
in Step 2
* Collect. Conversion is used to
determine the action you want to do in case of Material not available. This
will not be relevant when then Order is in creation phase
If Status Check is used, an
availability check does not have to run ever time an order is released. This
reduces the system load. (SAP help)
4. Define Change Documents,
Collective Purchase Requisition, MRP relevance
This configuration plays a vital role on checking the Material Availability in SAP PM.
You need to make sure Res / Pur Req is set Immediately, else
during Work Order Creation, Material availability check will not work.
Material Master data Maintenance
Availability Check 02 is maintained
for the Material.
Case 1 : Check availability during
Order creation
Scenario 1: Before Saving the Work
Order
A work order creation in progress,
after entering the Material availability icon highlighted below will give the
pop-up “Non-Availability of Material See log”
System Status MSPT – Material
Shortage will be updated.
Click the Log icon to see the
messages.
Click the Display log in Total to
view all messages.
Please make a note, this will not
stop you on saving the Work Order in CRTD status.
Scenario 2: After the Work Order is
saved
During creation System Status is set
as MANC (Material Availability not checked)
System Status MSPT (Material
Shortage) is set automatically on save.
Work Order can be reviewed using
System Status itself
Case 2 : Check availability during
Order release
Scenario 1: Define Inspection
Control – User decides on release if parts are missing
When the Order is created, material
planning is done and saved. Upon clicking the release flag, system gives below
message
Based on the configuration, user have
authority to bypass and release the order.
Click on Missing Parts List icon
Scenario 2: Define Inspection
Control – No release if parts is missing
When the release flag is clicked,
system pop-up below error message
In this configuration setting, you
cannot release the work order.
These are the very basic configuration to check material availability for PM order. More roaming on configuration will provide more scenarios.
**Cases are accumulated from other sources to elucidate the scenarios.
**Cases are accumulated from other sources to elucidate the scenarios.
Happy Learning